Initial Phase of New Warehouse project in Halesowen started in July ahead of the main build which starts at the end of the year.
The groundworks package involves over 270 - 600mm diameter piles to be sunk to 10m into ground to allow the 14,000 cubic metres of soil to be taken away by up to 4m deep for a new 42,000sqft high bay warehouse to be erected supported by a new staff car park.
Within the new warehouse will be 22,000sqft of new offices over 3 floors and another 38,000sqft of mezzanine storage over two floors. Gould Singleton Architects are acting as Projects Architects, Project Managers, Principle Designers for CDM and Building Regulations.
Contract value for all Phases - c£8m
We are pleased to have now secured full planning permission for a major new scheme in Halesowen for one of the Towns largest employers. Gould Singleton have acted as Project Managers and Project Architects and have now received instruction to take the scheme forward to detailed design and obtaining tenders for the scheme which is expected to be up to £7m construction value.
Our approach with the Local Authority, Local Businesses' and adjoining neighbours was transparent from the outset and started with a Public Forum in July 2022 where interested parties could view and comment on the proposals.
Work is planned to start at the end of the year
With the project at St John's Church, Harborne moving forward, we are pleased to show an exciting fly through of the new proposed design works.
Our thanks go to Rupert Blomfield for the animation and works to help present the scheme.