Casa de Wali

Casa de Wali **COMING IN 2025** Studio casita (550sqft) in La Enea, Guararé, Panamá. Our preferred contact method is via email.

We have added a link for our availability calendar and our Reservation Request Form which will go live closer to the first availability.

Most of the ceilings installed on the interior of the main structures.  The tile work has started with the bathrooms in ...
21/10/2024

Most of the ceilings installed on the interior of the main structures. The tile work has started with the bathrooms in the main house and the leveling for the floor tile is underway. The gutters are being painted and prepped for installation.

Additionally, the septic system rough dig is complete and the rock/gravel leach field area is in place. More tiling and work on the septic for the remainder of this week!

Again, lots of rain this week but progress continues.  Windows and glass blocks installed, just waiting to install the s...
17/10/2024

Again, lots of rain this week but progress continues. Windows and glass blocks installed, just waiting to install the screened vents for the glass block areas. Preparing to install gutters on both main structures. Pumphouse is 80% and fill starting to arrive for the grade.

The wires are getting pulled for the light fixtures inside to allow for the ceiling to get installed.

Everything is coming together!

09/10/2024

Getting things done!!

Lots of rain this week so the houses are getting base colors and the framing is getting erected for the ceilings.
09/10/2024

Lots of rain this week so the houses are getting base colors and the framing is getting erected for the ceilings.

Ongoing work on the metal framing for the roof of the main house this week.  Additionally, they have started to apply th...
24/08/2024

Ongoing work on the metal framing for the roof of the main house this week. Additionally, they have started to apply the smooth layer to the walls in areas in both structures. It changes more each passing day!!

More work while we are away!  Roofline beams for the carport ready to be poured and the roof panels are getting installe...
03/08/2024

More work while we are away! Roofline beams for the carport ready to be poured and the roof panels are getting installed on the casita.

The walls continue to grow on the main house and the metal roof framing has started for the casita!!
25/07/2024

The walls continue to grow on the main house and the metal roof framing has started for the casita!!

This week has been a continuation of the concrete pouring for vertical columns and the horizontal cross beams.  Also, go...
14/07/2024

This week has been a continuation of the concrete pouring for vertical columns and the horizontal cross beams. Also, got some string mock-ups over the main house to show roof lines and heights.

It looks better everyday!

Update:  The walls of both houses are rising and rough electrical is 90% complete.  Framing and pouring the columns thro...
04/07/2024

Update: The walls of both houses are rising and rough electrical is 90% complete. Framing and pouring the columns through the remainder of this week!

The weather cooperated and we got the slab/floor poured for the main house today!!
21/06/2024

The weather cooperated and we got the slab/floor poured for the main house today!!

Walls and rough electrical work going in for the Casita. It is hard to visualize all of the dimensions from 2D plans, bu...
20/06/2024

Walls and rough electrical work going in for the Casita. It is hard to visualize all of the dimensions from 2D plans, but after standing inside the walls, it’s really going to be a nice space.

Plus, v***r barrier and rebar preparation for pouring the slab of the Casa. If the weather cooperates, the slab will be finished this week!

Progress continues!!  Lots of rain over the last few days but today was nice enough to pour the slab/floor for the Casit...
17/06/2024

Progress continues!!

Lots of rain over the last few days but today was nice enough to pour the slab/floor for the Casita.

Our project is underway and we will keep everyone updated on the progress over the following months!!  We anticipate bei...
06/06/2024

Our project is underway and we will keep everyone updated on the progress over the following months!! We anticipate being ready for reservations around May 2025! Stay tuned!!

Dirección

La Enea
Guararé

Notificaciones

Sé el primero en enterarse y déjanos enviarle un correo electrónico cuando Casa de Wali publique noticias y promociones. Su dirección de correo electrónico no se utilizará para ningún otro fin, y puede darse de baja en cualquier momento.

Contato La Empresa

Enviar un mensaje a Casa de Wali:

Videos

Compartir