07/02/2024
截至113年2月4日,工程預定進度:61.56%,實際進度:62.04%。
主要施作工項:
1.旅服中心1-2F南側GRC版片施工。
2.旅服中心金屬屋頂北側屋頂防水膜施工。
3.旅服中心PVC屋頂PIR版吊料及外天溝施工。
4.旅服中心1F輕隔間止水墩施工。
5.旅服中心塔台電梯鋼構安裝。