11/07/2024
Been at the site all week..
Eight other unit owners and myself rented telehandler lift and hired a crew to get furniture and appliances up to our specified units..
Curbing is being formed today and will be poured on Saturday.
Paving crew is back at work installing pavers..
Lobby glass install will be completed by next Friday.
Still waiting on insurance adjuster to give the okay to demo those two small rooms at beach level and rebuild. That shouldn't slow us down as that total process should only take 4 weeks.
Power panel should arrive in a few weeks an estimations are one to two weeks to install.
Pool people will be out November 18th installing coping along the pool and new tile.
Waiting on their call back for new pool equipment and heater quote (Milton took out our brand new equipment).
We're hoping to have power back on and AC's running on or around December 20th..
By the next trip down on November 19th, our unit should be 100% done (remaining countertops, pull handles on cabinets and drawers, custom closets in both bedrooms)
On our November 19th trip, we will hang TVs and get everything else put away - and go shop to restock the entire kitchen with utensils, blenders, plates, glasses, etc..